Saudi Rabigh2 IPP Project

Power Plants Overseas

2013.12.01 ~ 2017.06.30

Construction cost: 1.21 billion USD
Decription: Capacity: 2100MW

[Power Plant]

The Rabigh 2 IPP Project is a project received the Saudi Electricity Company (SEC). This project includes constructing a 2100MW gas fired power plant in Rabigh, which is a city located 150㎞ north of Jeddah.
Samsung C&T formed a consortium with the Saudi Arabian Construction Company ARCC (Al Rushaid Construction Co., Ltd.) ACWA Power International. The consortium will deliver EPC (Engineering, procurement construction). Also through equity investment, Samsung C&T will gain a variety of different business models while managing operations being in charge of planning future business management.

- Capacity: 2100MW
- Construction Cost: 1.21 billion USD
- Construction Period: 2013. 12 ~ 2017. 6